Settings
Cost & Rebate
Fixed component: electrician, switchboard, paperwork (~$2,500–3,500).
Per-kWh component for cells/BMS ($600–900 typical).
Post-1 May 2026: Tier 2 (14–28 kWh) is 60% of Tier 1; Tier 3 (28–50) is 15%.
Battery assumptions
Synced with sidebars on Battery sizing and Quote pages.
Annual usable-capacity fade, entered as a percent.
Quiescent power draw of inverter/electronics; valued at the plan's time-weighted import tariff.
Shared power cap used for charging, discharge to load, and any intentional export.
DCF
The return you'd want elsewhere to beat this battery. Synced with Battery sizing and Quote.
FiT is assumed flat over time in the current model.
Optional terminal-year credit (depends on whether you'll repurpose or sell the unit).